[41457] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 6 - 136, 134 and 132 Panel DP-1 Shutdown Request for 1/19/9

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jan 14 14:15:29 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'juliec@mit.edu'" <juliec@MIT.EDU>,
        "'lnolan@math.mit.du'"
	 <lnolan@math.mit.du>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>, "'elp@mit.edu'" <elp@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'mbj@mit.edu'" <mbj@MIT.EDU>, "'guidess@mit.edu'" <guidess@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 14 Jan 1998 14:13:09 -0500

> To: 	juliec@mit.edu; lnolan@math.mit.du; schedule@mit.edu;
> elp@mit.edu; shutdowns@mit.edu; mbj@mit.edu; guidess@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 6 - 136, 134 and 132 Panel DP-1 Shutdown Request
> for 1/19/98
> 
> 
The following shutdown request for Bldg. 6 - 136, 134 and 132 electrical
shutdown request for 1/19 is for your informaton and comment. Would you
please let me know if this has your approval or not.

> Status: Normal
> Building: 6-136, 134 and 132
> Date: 1/19/98
> Day: Monday
> Time: 7:00 AM - 11:00 AM
> System: Electrical; power outlets and fan coil units located in 124,
> 126A, 123, 125, 128A, 128, 127, 130, 127, 132, 131, 134, 133, 138
> Duration: 4 hours
> Reason: 
> To tie in new 250 AMP circuit breaker - by outside contractor.
> 
> Effect: 
> Loss of building power: lighting, corridors/stairs, air: supply
> ventilation, supply cooling,  exhaust-general air
> 
> 