RE: Requested Rescheduled Shutdown for Bldgs. 6 (All, 4 - (Partia

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 8 10:06:45 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'duggins@math.mit.edu'"
	 <duggins@math.mit.edu>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'acherron@mit.edu'" <acherron@MIT.EDU>,
        "'centor@mit.edu'" <centor@MIT.EDU>,
        "'cwilkes@mit.edu'"
	 <cwilkes@MIT.EDU>,
        "'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
        "'jsheahan@mit.edu'" <jsheahan@MIT.EDU>,
        "'naylor@mit.edu'"
	 <naylor@MIT.EDU>,
        "'decarli@mit.edu'" <decarli@MIT.EDU>,
        "'lpaul@mit.edu'" <lpaul@MIT.EDU>,
        "'cdernay@mit.edu'" <cdernay@MIT.EDU>,
        "'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
        "'elp@mit.edu'"
	 <elp@MIT.EDU>, "'farideh@mit.edu'" <farideh@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        Cust-Coach
	 <cust-coach@MIT.EDU>,
        "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'cehart@mit.edu'" <cehart@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
        "'ndk@mit.edu'" <ndk@MIT.EDU>, "'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
        Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Date: Thu, 8 Jan 1998 10:04:32 -0500

Dear Everyone:
   Reminder ... this shutdown will take place tonight (1/8) at 11:00 PM
to tomorrow (1/9) at 7:00 AM.
	   Andrea Nichols
> Operations Center
> 8-7872
> 
> 	> Status: Normal
> 	> Building: 2 (All), 4 (Most) and 6 (All)
> 	> Date: 1/8 PM - 1/9 AM
> 	> Day: Thursday PM - Friday AM
> 	> Time: 11:00 PM (1/8) - 7:00 AM (1/9)
> 	> System: 2 (All 480V Power), 4 (most 208 V power and all 480V
> power and
> 	> 6 (All 208 and 480V power
> 	> Duration: 8 hours
> 	> Reason: 
> 	> To install new high voltage switchgear at electrical
> substations
> 	> 
> 	> Effect: 
> 	> Loss of Power: access control, bldg. power, elevators,
> computers,
> 	> telephones, lighting; Water: chilled water and de-ionized
> water; Air:
> 	> supply ventilation; supply cooling, supply heating,
> 	> exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam
> 	> condensate return and pumps (2nd shift to dump condensate)
> 	> 
> 	> 
> 
> 