[41395] in Hotline Meeting
RE: Requested Rescheduled Shutdown for Bldgs. 6 (All, 4 - (Partia
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 8 10:06:45 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'acherron@mit.edu'" <acherron@MIT.EDU>,
"'centor@mit.edu'" <centor@MIT.EDU>,
"'cwilkes@mit.edu'"
<cwilkes@MIT.EDU>,
"'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
"'jsheahan@mit.edu'" <jsheahan@MIT.EDU>,
"'naylor@mit.edu'"
<naylor@MIT.EDU>,
"'decarli@mit.edu'" <decarli@MIT.EDU>,
"'lpaul@mit.edu'" <lpaul@MIT.EDU>,
"'cdernay@mit.edu'" <cdernay@MIT.EDU>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'elp@mit.edu'"
<elp@MIT.EDU>, "'farideh@mit.edu'" <farideh@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'cehart@mit.edu'" <cehart@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
"'ndk@mit.edu'" <ndk@MIT.EDU>, "'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>
Date: Thu, 8 Jan 1998 10:04:32 -0500
Dear Everyone:
Reminder ... this shutdown will take place tonight (1/8) at 11:00 PM
to tomorrow (1/9) at 7:00 AM.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 2 (All), 4 (Most) and 6 (All)
> > Date: 1/8 PM - 1/9 AM
> > Day: Thursday PM - Friday AM
> > Time: 11:00 PM (1/8) - 7:00 AM (1/9)
> > System: 2 (All 480V Power), 4 (most 208 V power and all 480V
> power and
> > 6 (All 208 and 480V power
> > Duration: 8 hours
> > Reason:
> > To install new high voltage switchgear at electrical
> substations
> >
> > Effect:
> > Loss of Power: access control, bldg. power, elevators,
> computers,
> > telephones, lighting; Water: chilled water and de-ionized
> water; Air:
> > supply ventilation; supply cooling, supply heating,
> > exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam
> > condensate return and pumps (2nd shift to dump condensate)
> >
> >
>
>