Bldg. 38 - 001 Shutdown Request for 10/6

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 3 11:54:26 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: gfp170@mitrlevm.mit.edu
Cc: shutdown@plant.mit.edu, B-Zone <B-Zone@MIT.EDU>, shutdowns@MIT.EDU,
        schedule@MIT.EDU
Date: Fri, 3 Oct 1997 11:52:18 -0400

> To: 	gfp170@mitrlevm.mit.edu
> Cc: 	shutdown@plant.mit.edu; B-Zone; shutdowns@mit.edu;
> schedule@mit.edu
> Subject: 	Bldg. 38 - 001 Shutdown Request for 10/6
> 
> 
The following shutdown request for Bldg. 38 - 001 on 10/6 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 38-001 (or possibly entire building)
> Date: 10/6/97
> Day: Monday
> Time: 6:00 AM - 3:00 PM
> System: Heating hot water
> Duration: 8 hours
> Reason: 
> Tie in new reheat coil to system
> 
> Effect: 
> Loss of heating hot water in Rm. 001 only. Air Handler 1 is on the
> reheating system. If the new reheat coil isn't tied to the system
> easily then there will have to be a shutdown of all heat in Bldg. 38.
> Monday, 10/6 is supposed to comfortably warm (70 degrees)
> 
> 