[39810] in Hotline Meeting

home help back first fref pref prev next nref lref last post

FCS 2 - 10/3 or rain date of 10/7 shutdown request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 30 10:14:35 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: jmganno@MIT.EDU, shutdowns@MIT.EDU, lambert@mitvma.mit.edu,
        mcgrath@mtl.mit.edu, bob@hq.lcs.mit.edu
Cc: shutdown@plant.mit.edu
Date: Tue, 30 Sep 1997 10:12:39 -0400

> To: 	jmganno@mit.edu; shutdowns@mit.edu; lambert@mitvma.mit.edu;
> mcgrath@mtl.mit.edu; bob@hq.lcs.mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	FCS 2 - 10/3 or rain date of 10/7 shutdown request
> 
> 
The following FCS2 shutdown request for 10/3 or a rain date of 10/7 is
for your information and comment. Would you please let me know if this
has your approval or disapproval.

Thank you.

Andrea Nichols
Operations Center
 8-7872


> Status: Normal
> Building: Campus
> Date: 10/3/97
> Day: Friday
> Time: 10:00 AM - 1:00 PM
> System: FCS 2 Campus alarm monitoring system
> Duration: 3 hours
> Reason: 
> Back-up of FCS2 campus alarm monitoring system data
> 
> Effect: 
> Loss of campus alarm monitoring sytem. Each group will be responsible
> for its own space.
> 
> 