FW:Approved -- Bldgs. 2, 4, & 6 Shutdown Request for 9/25

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 19 15:30:27 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
        C-Zone
	 <C-Zone@MIT.EDU>, sdverify@MIT.EDU,
        Jack Mannion
	 <JMannion@PLANT.MIT.EDU>
Cc: shutdown@plant.mit.edu, shutdown@MIT.EDU
Date: Fri, 19 Sep 1997 15:28:02 -0400

The following approved shutdown for Bldgs. 2, 4 & 6 on 9/25 is for your
information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: 2-001, 007, 011, 013 (HVAC & Process Laser Cooling/; 2-019
> > (HVAC); 4-082 & 070 (HVAC)& 6-035 HVA C 
> > Date: 9/25/97
> > Day: Thursday
> > Time: 7:00 AM - 3:00 PM
> > System: Primary chilled water supply and return serving HVAC as Fan
> > Coil Units and process laser cooling
> > Duration: 8 hours
> > Reason: 
> > Installation of new supply and return branch lines in 2-007; to
> serve
> > new laser cooling application
> > 
> > Effect: 
> > Loss of chilled water
> > 
> > 
> 