FW:Approved -- Bldg. 54 - 1311, 1319, 1323 and 1327 Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 19 10:37:24 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU, cust-coach@MIT.EDU,
        opsnote@MIT.EDU, Steven Gilligan
	 <sgilliga@PLANT.MIT.EDU>,
        garyk@MIT.EDU, ltmolina@MIT.EDU, A-Zone
	 <A-Zone@MIT.EDU>,
        sdverify@MIT.EDU, relices@MIT.EDU
Cc: shutdown@MIT.EDU, shutdowns@MIT.EDU
Date: Fri, 19 Sep 1997 10:35:38 -0400

The following approved shutdown for Blgd. 54 - labs 1311, 1319, 1323 and
1327 on 9/27 is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: 54 - 1311, 1319, 1323 & 1327
> > Date: 9/27/97
> > Day: Saturday
> > Time: 6:00 AM - 4:00 PM
> > System: 2 Electrical Panels for above listed rooms
> > Duration: 10 hours
> > Reason: 
> > Change panel interiors for added HVAC equipment
> > 
> > Effect: 
> > Loss of building power and power in labs listed above
> > 
> > 
> 