[39593] in Hotline Meeting
Bldg. 54 - 1311, 1319, 1323 and 1327 Shutdown Request for either
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 15 16:19:59 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: relices@MIT.EDU, shutdowns@MIT.EDU, cust-coach@MIT.EDU, opsnote@MIT.EDU,
A-Zone <A-Zone@MIT.EDU>
Cc: shutdown@plant.mit.edu
Date: Mon, 15 Sep 1997 16:18:32 -0400
> To: relices@mit.edu; shutdowns@mit.edu; cust-coach@mit.edu;
> opsnote@mit.edu; A-Zone
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 54 - 1311, 1319, 1323 and 1327 Shutdown Request
> for either 9/27 or 10/4 (Saturday)
>
>
The following shutdown request for Bldg. 54 - 1311, 1319, 1323 and 1327
on either 9/27 or 10/4 is for your information and comment. Would you
please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 54 - 1311, 1319, 1323 & 1327
> Date: 9/27/97
> Day: Saturday
> Time: 6:00 AM - 4:00 PM
> System: 2 Electrical Panels for above listed rooms
> Duration: 10 hours
> Reason:
> Change panel interiors for added HVAC equipment
>
> Effect:
> Loss of building power and power in labs listed above
>
>