FW:Approved Bldg. 41 Shutdown Requst - 6/12 PM - 6/13 AM

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 3 09:25:20 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: William Wohlfarth <wpwohlfa@PLANT.MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        "'sdverify@mit.edu'" <sdverify@MIT.EDU>
Cc: Neil Tomlinson <NTomlins@PLANT.MIT.EDU>, 'shutdowns'
	 <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
        "'delsemil@mit.edu'" <delsemil@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>
Date: Tue, 3 Jun 1997 09:26:07 -0400

The following approved shutdown request for Bldg. 41 from 6/12 PM thru
6/13 AM is for your information.

>Thank you.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>Status: Normal
>Building: 41
>Date: 6/12/13
>Day: Thursday
>Time: 11:00 PM - 7:00 AM
>System: Normal Electrical Power
>Duration: 8 hours
>Reason: 
>New substation cutover
>
>Effect: 
Loss of  power: access controls, building, elevators, computers,
>telephones, lighting and corridors/stairs lighting. Air: supply ventilation,
>supply cooling and heating, laboratory exhaust, general exhaust, toilet
>exhaust, compressed control, compressed lab and lab vacuum air; Steam:
>condensate return steam; Water: chilled water (air conditioning).
>
>
>