[38517] in Hotline Meeting
Bldg. E10 - 236 - 243 Shutdown Request - 6/3
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 29 10:17:44 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andrea@wccf.mit.edu'" <andrea@wccf.mit.edu>,
"'dkurtz@mit.edu'"
<dkurtz@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'judithr@wccf.mit.edu'" <judithr@wccf.mit.edu>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Thu, 29 May 1997 10:19:34 -0400
>To: andrea@wccf.mit.edu; dkurtz@mit.edu; schedule@mit.edu;
judithr@wccf.mit.edu
Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
Subject: Bldg. E10 - 236 - 243 Shutdown Request - 6/3
The following shutdown request for Bldg. E10 - 236 - 243 (but will
affect entire building) on 6/3 is for your information and comment.
Would you please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Status: Normal
Building: E10 - 236 - 243 (also entire bldg.)
Date: 6/3/97
Day: Tuesday
Time: 7:30 AM - 3:00 PM
System: All hot and cold water;drainage
Duration: 7 hours
Reason:
Relocatiing pipe/capping off.
Effect:
>Loss of hot domestic and lab process water; cold domestic and lab process
>water. No restroom facilities, kitchen faucets, showers, drinking fountains,
lab water and sanitary drainage will be available during shutdown.