Bldg. E25 Shutdown Request - Sunday, 6/1
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 28 08:59:23 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'Andrea@wccf.mit.edu'" <Andrea@wccf.mit.edu>,
"'BENGEL@MIT.EDU'"
<BENGEL@MIT.EDU>,
"'dkurtz@mit.edu'" <dkurtz@MIT.EDU>,
"'andrea@wccf.mit.edu'" <andrea@wccf.mit.edu>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdl-adm-lib@it.edu'"
<sdl-adm-lib@it.edu>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 28 May 1997 09:01:00 -0400
>To: Andrea@wccf.mit.edu; BENGEL@MIT.EDU; dkurtz@mit.edu;
>andrea@wccf.mit.edu; jmganno@mit.edu; shutdowns@mit.edu; schedule@mit.edu;
sdl-adm-lib@it.edu
Cc: shutdown@plant.mit.edu
Subject: Bldg. E25 Shutdown Request - Sunday, 6/1
The following shutdown request for Bldg. E25 on 6/1 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Status: Normal
Building: E25
Date: 6/1/97
Day: Sunday
Time: 6:00 AM - 4:00 PM
System: Cold and Hot Domestic Water
Duration: 10 hours
Reason:
Check for cross connections between domestic and lab process water
Effect:
>Loss of use of cold and hot domestic water (no restroom facilities, drinking
fountains and kitchen faucets available during shutdown).