[38470] in Hotline Meeting
Re: Shutdown Request - Bldg. 11 - 5/27 PM - 5/28 AM
daemon@ATHENA.MIT.EDU (Jean E. Greene)
Thu May 22 13:58:18 1997
Date: Thu, 22 May 97 13:57:41
From: jean@MIT.EDU (Jean E. Greene)
To: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
Cc: Shutdowns@MIT.EDU, jdb@MIT.EDU, sdiamond@MIT.EDU, jean@MIT.EDU,
c-zone@MIT.EDU
This should not be a problem for the I/T Support staff members on the second and
third floors of Building 11. I will forward your email to them so all involved
are advised.
Thanks,
Jean
> Date: Thu, 22 May 1997 12:14 EDT
> From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
> Subject: Shutdown Request - Bldg. 11 - 5/27 PM - 5/28 AM
> To: Shutdowns@MIT.EDU, jdb@MIT.EDU, sdiamond@MIT.EDU, jean@MIT.EDU,
> c-zone@MIT.EDU
> X-Envelope-To: c-zone@mit.edu, jdb@mit.edu, jean@mit.edu, sdiamond@mit.edu,
> Shutdowns@mit.edu
> X-Vms-To:
> IN%"Shutdowns@mit.edu, jdb@mit.edu, sdiamond@mit.edu, jean@mit.edu, c-zone@mit.
> edu"
> X-Vms-Cc: OPCTEMP2
>
> The following requested shutdown for Bldg. 11 on 5/27 PM - 5/28 AM is
> for your information and comment. Would you please let me know if this
> has your approval or not.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> Building: 11
> System: Domestic Cold Water
> Date: 5/27 PM - 5/28 AM
> Day: Tuesday PM - Wednesday AM
> Time: 10:00 PM (Tuesday) - 4:00 AM (Wednesday)
> Duration: 6 hours
> Reason: Have to shift a water line pipe on 1st floor
> Effect: Loss of domestic cold water only (would affect restroom
> facilities, drinking fountains and kitchen faucets).