[38466] in Hotline Meeting
Shutdown Request - Bldg. 11 - 5/27 PM - 5/28 AM
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu May 22 12:18:53 1997
Date: Thu, 22 May 1997 12:14 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: Shutdowns@MIT.EDU, jdb@MIT.EDU, sdiamond@MIT.EDU, jean@MIT.EDU,
c-zone@MIT.EDU
X-Envelope-To: c-zone@mit.edu, jdb@mit.edu, jean@mit.edu, sdiamond@mit.edu,
Shutdowns@mit.edu
X-Vms-To:
IN%"Shutdowns@mit.edu, jdb@mit.edu, sdiamond@mit.edu, jean@mit.edu, c-zone@mit.
edu"
The following requested shutdown for Bldg. 11 on 5/27 PM - 5/28 AM is
for your information and comment. Would you please let me know if this
has your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
Building: 11
System: Domestic Cold Water
Date: 5/27 PM - 5/28 AM
Day: Tuesday PM - Wednesday AM
Time: 10:00 PM (Tuesday) - 4:00 AM (Wednesday)
Duration: 6 hours
Reason: Have to shift a water line pipe on 1st floor
Effect: Loss of domestic cold water only (would affect restroom
facilities, drinking fountains and kitchen faucets).