Bldg. 66 - North Side Labs - - 5/15

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 14 10:04:34 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lindlore@mit.edu'" <lindlore@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
        A-Zone <A-Zone@MIT.EDU>
Date: Wed, 14 May 1997 10:05:53 -0400

To: 	lindlore@mit.edu; shutdowns@mit.edu
Cc: 	shutdown@plant.mit.edu; cust-coach@mit.edu; A-zone@mit.edu
Subject: 	Bldg. 66 - North Side Labs - - 5/15


The following Critical shutdown request for Bldg. 66 - Northside Labs -
All Floors on 5/15 is for your information and comment. Would you please
let me know if this has your approval or disaproval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872 

Status: Critical
Building: 66 - North Side Labs - all floors
Date: 5/15/97
Day: Thursday
Time: 4:00 PM - 9:00 PM
System: Air Handler 1 - Chill Water Coils
Duration: 5 hours
Reason: 
>Continuation of repair or replacement work on chill water coils on Air
Handler 1.

Effect: 
Continued loss of supply ventilation and cooling from Air Handler 1.