Cancelled - Shutdown Request - Bldg. 26 Normal electrical power - 5/17

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed May 7 15:09:07 1997

Date: Wed, 7 May 1997 15:07 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, adams@mitlns.mit.edu,
        gfp170@mitrlevm.mit.edu, blair@MIT.EDU, b-zone@MIT.EDU
X-Envelope-To: b-zone@mit.edu, blair@mit.edu, schedule@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, schedule@mit.edu, adams@mitlns.mit.edu, gfp170@mitrlevm.
   mit.edu, blair@mit.edu, b-zone@mit.edu"

The following requested shutdown for Bldg. 26 on 5/17 has been
cancelled for now because of upcoming review periods and exams (thank
you Peter). We will reschedule this request sometime after graduation.

Thank you for your patience.

Andrea Nichols
Operations Center
8-7872

Building:       26
System:         Normal electrical power
Date:           TBD (after graduation in June)
Day:            Saturday
Time:           7:00 AM - 5:00 PM
Duration:       10 hours
Reason:         Upgrade high voltage switch
Effect:         Loss of Power: access controls, building power,
                elevators, computers, telephones and lighting;
                Water: chilled water;
                Air: supply ventilation, supply cooling, supply
                heating, laboratory exhaust air, general exhaust
                air, toilet exhaust air, compressed control air,
                compressed lab air and lab vaccum air;
                steam: condensate return.