[37785] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown Requst - Bldg. 68 Floors 1 thru 6 - 4/26

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Apr 9 09:44:05 1997

Date: Wed, 9 Apr 1997 09:43 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: jfucillo@MIT.EDU, shutdowns@MIT.EDU, jnarcotta@MIT.EDU, shyoung@MIT.EDU
X-Envelope-To: jfucillo@mit.edu, jnarcotta@mit.edu, shutdowns@mit.edu,
 shyoung@mit.edu
X-Vms-To: 
 IN%"jfucillo@mit.edu, shutdowns@mit.edu, jnarcotta@mit.edu, shyoung@mit.edu"

The following shutdown request for Bldg. 68 floors 1 thru 6 on 4/26 is
for your information and comment. Would you please let me know if this
has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       68 - Floors 1 thru 6
System:         Air Handlers 1, 2 and 3 (supply ventilation, cooling
                and heating)
Date:           4/26
Day:            Saturday
Time:           7:00 AM - 3:00 PM
Duration:       8 hours
Reason:         Access to damper actuators. To be able to service
                dampers and actuators.
Effect:         Loss of supply ventilation, cooling and heating during
                shutdown period.