[37777] in Hotline Meeting
Shutdown Request - Building 3 - 4/10
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Apr 8 16:22:05 1997
Date: Tue, 8 Apr 1997 16:21 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, admitmb@mitvmc.mit.edu,
jobrien@MIT.EDU, dory@MIT.EDU, pmccosco@MIT.EDU, chm@MIT.EDU,
annab@MIT.EDU, mamullow@MIT.EDU, cust-coach@MIT.EDU, ndk@MIT.EDU,
fenner@MIT.EDU
X-Envelope-To: annab@mit.edu, chm@mit.edu, cust-coach@mit.edu, dory@mit.edu,
fenner@mit.edu, jobrien@mit.edu, mamullow@mit.edu, ndk@mit.edu,
pmccosco@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, admitmb@mitvmc.mit.edu, jobrien@mit.ed
u, dory@mit.edu, pmccosco@mit.edu, chm@mit.edu, annab@mit.edu, mamullow@mit.e
du, cust-coach@mit.edu, ndk@mit.edu, fenner@mit.edu"
The following requested shutdown for Bldg. 3 for 4/10 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 3 (all rooms)
System: Low Pressure Steam (heating)
Date: 4/10
Day: Thursday
Time: 10:00 AM - 2:00 PM
Duration: 4 hours
Reason: Replace radiator valve in Room 305F
Effect: Loss of heat during shutdown period.