home help back first fref pref prev next nref lref last post

Rescheduled Requested Shutdown - FCS2 system - Now for 4/10

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Apr 7 14:24:28 1997

Date: Mon, 7 Apr 1997 14:23 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: jmganno@MIT.EDU, shutdowns@MIT.EDU, lambert@mitvma.it.edu,
        mcgrath@mtl.mit.edu, bob@hq.lcs.mit.edu
X-Envelope-To: jmganno@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"jmganno@mit.edu, shutdowns@mit.edu, lambert@mitvma.it.edu, mcgrath@mtl.mit.
   edu, bob@hq.lcs.mit.edu"

The following rescheduled shutdown request for FCS2 now for 4/10 is
your information and comment. Would you please let me know if these
have your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       Campus
System:         FCS2
Date:           4/10 (formerly requested for 4/8)
Day:            Thursday (formerly requested for Tuesday)
Time:           10:00 AM - 1:00 PM
Duration:       3 hours
Reason:         Preventive maintenance work on FCS2 system.
Effect:         Loss of alarm monitoring system via FCS2 system.