Requested Shutdown - Bldg. E34 - Entire Bldg. - 4/10 and 11

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Apr 3 14:21:36 1997

Date: Thu, 3 Apr 1997 14:20 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, relices@MIT.EDU
X-Envelope-To: relices@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, relices@mit.edu"

The following requested shutdown for Bldgs. E34 on 4/10 and 11 is for
your information and comment. Would you please let me know if this has
your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       E34 - Entire Bldg.
System:         Heating
Date:           4/10 and 11
Day:            Thursday and Friday
Time:           8:00 AM Thursday to 3:00 PM Friday
Duration:       31 hours
Reason:         Installation of gas burner
Effect:         Loss of low pressure steam, condensate return and
                heating hot water.

                Note:  Will reschedule is weather is severe (under 40
                degrees).