Requested Shutdown - Bldg. 26-100 - 11/22/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Nov 15 08:17:29 1996

Date: Fri, 15 Nov 1996 08:16 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU
X-Envelope-To: schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, schedule@mit.edu"

The following requested shutdown for Bldg. 26-100 for 11/22 is for your
information and comment. Would you please let me know if this has your
approval or disapproval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Building:       26-100
System:         Air Handler 1 System, Chilled Water Coil, Fan
Date:           11/22/96
Day:            Friday
Time:           7:00 AM - 1:00 PM
Duration:       6 hours
Reason:         Repair AH1 cooling coil drainage system (PM#701600
                located in 26-004)
Effect:         Loss of chilled water, supply ventilation, cooling
                and heating during shutdown period.

                Note:  If the temperature is particularly cold outside
                this work would be rescheduled. It is also supposed
                to be much warmer next week (according to Bruce!).