Requested Shutdown - All of E15 - Filters Changed - 11/19/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Nov 14 14:29:54 1996
Date: Thu, 14 Nov 1996 14:28 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, dirving@media.mit.edu, bv@media.mit.edu,
haller@media.mit.edu, jroll@MIT.EDU
X-Envelope-To: jroll@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, dirving@media.mit.edu, bv@media.mit.edu, haller@media.mi
t.edu, jroll@mit.edu"
The following requested shutdown for E15 for 11/19 is for your
information and comment. Would you please let me know if this has your
approval or disapproval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
Building: E15 - All Floors, Film Video Theater, Lobby and Atrium
System: Air Handler 1, 2, 3 and 4, Supply Fans 1A and 1B
Date: 11/19/96
Day: Tuesday
Time: 9:00 AM - 10:15 AM
Duration: 1-1/4 hours
Reason: Change Filters
Effect: Loss of supply-ventilation as follows: for AH1 A & B -
these will be down for 20 minutes each. For AH 2 and
3, these will be down for 15 minutes each.
Note: While one air handler is down, all others will be
operational.