[35636] in Hotline Meeting
Requested Shutdown - Bldgs. 31 and 17A - 11/11/96
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Nov 5 13:49:30 1996
Date: Tue, 5 Nov 1996 13:48 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, schedule@MIT.EDU, bcorkum@MIT.EDU, ameswf@MIT.EDU,
pcollymo@MIT.EDU
X-Envelope-To: ameswf@mit.edu, bcorkum@mit.edu, pcollymo@mit.edu,
schedule@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, schedule@mit.edu, bcorkum@mit.edu, ameswf@mit.edu, pcoll
ymo@mit.edu"
The following requested shutdown of Bldgs. 31 and 17A for 11/11 is for
your information and review. Would you please let me know if this has
your approval or disapproval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
Building: 31 and 17A (entire buildings)
System: Dometic hot and cold water/hot and cold lab process
water/ lab compressed air (this is water-cooled)
Date: 11/11/96
Day: Monday
Time: 9:00 AM - 3:00 PM
Duration: 6 hours
Reason: Tie-in of containment backflow preventer
Effect: Loss of all hot domestic, hot lab process, cold
domestic, cold lab process water and compressed lab air.
17A compress air system; (150 HP Sullair - 31 bsmt, high
pressure Ingersall-Rand - 31 bsmt that serves 31 & 17