Request for Shutdown - Bldg. E51 - Basement

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue May 21 13:18:51 1996

Date: Tue, 21 May 1996 13:16 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, cust-coach@MIT.EDU, schedules@MIT.EDU,
        e-zone@MIT.EDU, mmarshal@MIT.EDU, hmadnic@MIT.EDU, mdimauro@MIT.EDU,
        dwp@mitvma.mit.edu
X-Envelope-To: cust-coach@mit.edu, e-zone@mit.edu, hmadnic@mit.edu,
 mdimauro@mit.edu, mmarshal@mit.edu, opsnote@mit.edu, schedules@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, opsnote@mit.edu, cust-coach@mit.edu,schedules@mit.edu, e
   -zone@mit.edu, mmarshal@mit.edu, hmadnic@mit.edu, mdimauro@mit.edu, dwp@mitvm
   a.mit.edu"

The following request for shutdown for E51 - basement is for your
review and information. Would you please advise me if this is
acceptable or unacceptable either via return e-mail or phone me at 8-6651.

Thanks very much.

Andrea
Operations
Physical Plant

Building:       E51 Basement (new #s shown) 053, 057, 050, 061, 063,
                064, 066J, 068, 069, 070, 075, 078, 085, 090, 091, 093, 095,
                094, 098
System:         Exhaust general air
Date:           5/31 - 6/3
Day:            Friday - Sunday
Time:           6:00 PM Friday - 7:00 AM - Sunday
Duration:       37 hours
Reason:         Asbestos removal - access to basement will not be
                allowed.
Effect:         No access to any room  - shutdown of exhaust air.