Approved Shutdown - Building E40

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri May 17 14:51:09 1996

Date: Fri, 17 May 1996 14:49 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, dcarlson@MIT.EDU, cappucci@MIT.EDU, e-zone@MIT.EDU,
        sdverify@MIT.EDU
X-Envelope-To: cappucci@mit.edu, dcarlson@mit.edu, e-zone@mit.edu,
 sdverify@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, dcarlson@mit.edu, cappucci@mit.edu, e-zone@mit.edu, sdve
   rify@mit.edu"

The following approved shutdown is for your information.

Thanks for your assistance.
Andrea Nichols
Operations

Building:       E40 (Core of Building)
System:         Air Handler 1 (#707017)
Date:           5/23/96
Day:            Thursday
Time:           7:00 AM - 9:00 AM
Duration:       2 hours
Reason:         Filter change
Effect:         Loss of supply-ventilation, supply cooling and supply-
                heating during shutdown.