[33107] in Hotline Meeting
4/22/96 Power Interruptions
daemon@ATHENA.MIT.EDU (Dan Crovo,MIT E19-134A,253-4660)
Mon Apr 22 15:07:57 1996
Date: Mon, 22 Apr 1996 13:44 EDT
From: "Dan Crovo,MIT E19-134A,253-4660" <DCROVO%MITPPL.bitnet@mitvma.mit.edu>
To: plant-notify@MIT.EDU
X-Envelope-To: plant-notify@mit.edu
X-Vms-To: IN%"plant-notify@mit.edu"
April 22, 1996 @ 1:45 pm
At approximately 1:21 pm there was a cable fault on the Comm Electric
system that affected the M.I.T. campus. There were several power dips
and at this time it is not clear if the electrical system is stable.
As additional information becomes available it will be forwarded to you
via Email. This same information will be put on the Physical Plant
Emergency Information line, ext. 3-1300.
Dan Crovo for Mary Tobin, Operations Center