[33100] in Hotline Meeting
Requested Shutdowns - W85 - April 24, 1996
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Mon Apr 22 09:42:41 1996
Date: Mon, 22 Apr 1996 09:41 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU, collins@MIT.EDU
X-Envelope-To: collins@mit.edu, mmahoney@mit.edu, opsnote@mit.edu,
shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, collins@mit.edu"
The following are requested shutdowns for W85 for your review and
information. Would you please advise if these are acceptable either by return
e-mail or call me at 8-6651 at your earliest convenience.
Thanks and I look forward to hearing from you.
Andrea
Building: W85 - All (high rise and low rise)
System: All electric power and lighting
Date: 4/24/96
Day: Wednesday
Time: 11:30 - noon
Duration: 15 minutes between 11:30 and 12 noon
Reason: To tie into main switchgear
Effect: Loss of all power (access controls, emergency power,
building power, elevators, computers, telephones, lighting,
corridors, stairs; water - chilled water, heating hot water; air
-supply-ventilation, cooling, heating, exhaust laboratory,
exhaust-general, exhaust-toilet, compressed air, and
steam-condensate return.
Building: W85 - Highrise only
System: Emergency power and elevators
Date: April 24, 1996
Day: Wednesday
Time: 9:00 AM - 11:00 AM
Duration: 2 hours
Reason: To install new panel
Effect: Loss of emergency power and elevator power.