Requested Shutdowns - Bldgs. 1, 3 & 5 (d'Arbeloff Lab)
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Apr 17 15:10:56 1996
Date: Wed, 17 Apr 1996 15:07 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: fenner@MIT.EDU, shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU,
cust-coach@MIT.EDU
X-Envelope-To: cust-coach@mit.edu, fenner@mit.edu, mmahoney@mit.edu,
opsnote@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"fenner@mit.edu, shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, cust-
coach@mit.edu"
The following is information pertaining to the requested shutdowns for
Blgs. 1, 3 & 5 for your review and approval. Please advise via return
e-mail or telephone me at 8-6651 if these are acceptable. Thanks.
Andrea
Building: 1, 3, 5 (d'Arbeloff Lab)
System: Low Pressure steam - no heat
Date: 5/1/96
Day: Wednesday
Time: 7:00 AM - 3:00 PM
Duration 8 hours
Reason: To Tie into exiting lines. Shut off valve 3T in valve
chamber. (Bldg. 3 - motorized valve).
Effect: Loss of heat
Building: 1, 3, 5 (d'Arbeloff Lab)
System: Chilled Water - no air conditioning
Date: 4/29/96
Day: Monday
Time: 7:00 AM - 3:00 PM
Duration: 8 hours
Reason: Need to tie in existing lines.
Effect: No chilled water to 1-103, 104, 106, 107, 108, 110, 112
and 115.