Requested Shutdownfor 66-408

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Thu Apr 11 13:40:39 1996

Date: Thu, 11 Apr 1996 13:39 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, mmahoney@MIT.EDU, lindlore@MIT.EDU
X-Envelope-To: lindlore@mit.edu, mmahoney@mit.edu, opsnote@mit.edu,
 shutdowns@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, opsnote@mit.edu, mmahoney@mit.edu, lindlore@mit.edu"

The following pertains to the requested shutdown for Bldg. 68-08 and is
for your review and information.  Please advise me, at your earliest
convenience, if this would be acceptable either by return e-mail or
phone me at 8-6651.

Thanks and I look forward to hearing from you.
Andrea

Building:       66-408
System:         Chilled Water
Date:           4/16/96
Day:            Tuesday
Time:           7:30 AM - 1:30 PM
Duration:       6 hours
Reason:         Have to tie in new unit.  Lab chilled water pump in 66-6th
                floor mechanic rm. will have to be secured. High pressure
                (l00PSI) lab air compressors are cooled by chilled water and
                will have to be secured; no high pressure compressed
                air to the building. Low pressure (40 PSI) service will not
                be affected.
Effect:         Loss of chilled water for air conditioning and pressure
                cooling for entire building.