[27879] in Hotline Meeting
SHUTDOWN BLDS 62,64
daemon@ATHENA.MIT.EDU (OPCTEMP%MITPPL.BITNET@mitvma.mit.e)
Fri Apr 14 09:51:02 1995
Date: Fri, 14 Apr 1995 09:48 EDT
From: OPCTEMP%MITPPL.BITNET@mitvma.mit.edu
To: DCARLSON@MIT.EDU, CAPPUCCI@MIT.EDU, SHUTDOWNS@MIT.EDU, OPSNOTE@MIT.EDU
Cc: SDVERIFY@MIT.EDU
X-Envelope-To: CAPPUCCI@MIT.EDU, DCARLSON@MIT.EDU, OPSNOTE@MIT.EDU,
SDVERIFY@MIT.EDU, SHUTDOWNS@MIT.EDU
X-Vms-To:
IN%"DCARLSON@MIT.EDU",IN%"CAPPUCCI@MIT.EDU",IN%"SHUTDOWNS@MIT.EDU",IN%"OPSNOTE@
MIT.EDU"
THE FOLOWIING IS AN ELECTRICAL SHUTDOWN
ROUTINE:
BLDG: 62,64
SYSTEM: ALL ELECTRIC POWER AND LIGHTING
DATE: 4/25/95
DAY: TUESDAY
TIME: 9:30 AM - 10:00 PM
DURATION: 30 MINUTES
REASON: UPGRADE CIRCUIT BREAKER UNIT
EFFECT: NO ELECTRIC POWER OR LIGHTING FOR 30 MINUTES
THIS SHUTDOWN IS A PREVIOUSLY E-MAILED ONE THAT HAD TO RESCHEDUALED
ROUTINE:
BLDG: 50, 51
SYSTEM: ALL ELECTRIC POWER AND LIGHTING
DATE: 4/26/95
DAY: WEDNSDAY
TIME: 6:30 AM - 7:00 AM
DURATION: 30 MINUTES
REASON: UPGRADE CIRCUIT BREAKER UNIT
EFFECT: NO ELECTRIC POWER OR LIGHTING FOR 30 MINUTES