[12413] in Hotline Meeting
Re:Cleared these -- Jerry
daemon@ATHENA.MIT.EDU (Jerry Burke)
Wed Dec 16 12:28:52 1992
Date: Wed, 16 Dec 92 12:32:51 EST
From: burke@MIT.EDU (Jerry Burke)
To: bigsteve@MIT.EDU (Steven M. Riester)
Cc: shutdowns@MIT.EDU
> Date: Wed, 16 Dec 92 10:29:34 EST
> From: bigsteve@MIT.EDU (Steven M. Riester)
> To: shutdowns@MIT.EDU
> Subject: Bldg 54 & 62 Dom. hot water and heat, 12/18
>
>
> Got a call from Phys Plant, they need an okay. There will be a
shutdown of high pressure steam in bldgs 54 and 62 from midnight Friday
December 18 to 6pm Sunday December 20. This will affect domestic heat
and hot water.
Got a call from Phys Plant, they need an okay. The elevator in bldg 24
will be out of commission from 8am to 4pm on Tuesday december 29.
Got a call from Phys Plant, they need an okay. The lab air compressor
in bldg 18 will be down from 7:30am to 11:30am on Wednesday December 30.
There will be no lab air that day.
What: Chilled Water Shutdown - There will be no cooling
When: Tuesday, 12/29, 8am-3pm
Where: Bldg. 54 Affects: ** Computer Rooms- 54-419, 54-527, 54-715
Cleaning Rooms- 54-1113, 54-1117
Offices- 54-1013, 54-1127
Please call LeeAnn, 3-1500 and give okay.
jerry