electrical shutdowns -- Cleared these
daemon@ATHENA.MIT.EDU (Jerry Burke)
Fri Dec 11 09:18:20 1992
Date: Fri, 11 Dec 92 09:22:13 EST
From: burke@MIT.EDU (Jerry Burke)
To: shutdowns@MIT.EDU
Craig called from Physical
Dec 29 from 7am to 7:10am Electrical Power and lighting shutdown in
Bldg. 8, 12 and 24 lab only.
Reason normal feed repaired, switching back to normal feed.
DEC 29, Bldg. 31 West and 43 from 7:30 to 7:40 , 208 and 120volt
affected
Dec 29, Bldg. 33, 35 31 and 41a from 7:30 to 7:40 entire building
shutdown all power and lighting.
Dec. 14, Bldg 39 from 11pm to 7am -- recycling fans.
Dec 15, Bldg W91 from 8:30 to 9am Dave Lambert is aware.....