Re: Power outages for Saturday Dec. 5th -- cleared all but #2 Jerry
daemon@ATHENA.MIT.EDU (Jerry Burke)
Tue Dec 1 11:25:23 1992
Date: Tue, 01 Dec 92 11:28:50 EST
From: burke@MIT.EDU (Jerry Burke)
To: shutdowns@MIT.EDU
Cc: mory@MIT.EDU
> From: chris@MIT.EDU
> Date: Tue, 1 Dec 92 08:43:25 EST
> To: shutdowns@MIT.EDU
> Subject: Power outages for Saturday Dec. 5th
> Cc: network@MIT.EDU
>
> PhysPlant called with these Tuesday at 8:20.
>
>1. Power in buildings 26,20,31,4,2, and 70 to be shut down from
8am-6pm.
> I did not okay this one. We may want to push back with this
> short a notice.
>
> 2. Power in buildings 33,35,31(west),41,41A,43 to be shut down from
> 7:30-7:40 am. I okay'ed this for the network group. december
5
>
>3. Power in buildings 8,12, and 24. I okay'ed this one as well for
the
> network group. The UPS in 24 should hold the network up for