[10844] in Hotline Meeting
RE:Bldg. 5 net config
daemon@ATHENA.MIT.EDU (jjmorey@Athena.MIT.EDU)
Thu Sep 24 09:22:11 1992
From: jjmorey@Athena.MIT.EDU
To: chris@Athena.MIT.EDU
Cc: hotline@Athena.MIT.EDU, dcns-cluster@Athena.MIT.EDU, ops@Athena.MIT.EDU,
Date: Thu, 24 Sep 92 09:21:49 EDT
Hi Chris-
Will this work have any effect on the bldg. 1 clusters (142/115)?
If so 1-142 will need to be closed down untill work complete and
as for 1-115 they would have to give an ok for 1-115 to be down.
Can you get back to me ASAP on this.
Thanks
JJ
Received: from MIT.MIT.EDU by po7.MIT.EDU (5.61/4.7) id AA12904; Tue, 22 Sep 92 17:26:03 EDT
Received: from BLARNEY.MIT.EDU by MIT.EDU with SMTP
id AA17240; Tue, 22 Sep 92 17:24:55 EDT
From: chris@MIT.EDU
Received: by blarney.MIT.EDU (4.1/4.7) id AA16803; Tue, 22 Sep 92 17:24:52 EDT
Date: Tue, 22 Sep 92 17:24:52 EDT
Message-Id: <9209222124.AA16803@blarney.MIT.EDU>
To: netusers@MIT.EDU
Cc: net-help@MIT.EDU, network@MIT.EDU
Subject: Building 5 Reconfiguration
Network Operations will be performing a reconfiguration of the
building 5 (18.58) network this Thursday at 8:00pm. Users are
unlikely to see any major interruptions in service, and the work
should be complete by 8:30pm.
- -Chris Murphy
MIT Network Operations
------- End of Forwarded Message
-------------------------------------------------------
From: chris@MIT.EDU
Received: by blarney.MIT.EDU (4.1/4.7) id AA17014; Wed, 23 Sep 92 17:30:29 EDT
Date: Wed, 23 Sep 92 17:30:29 EDT
Message-Id: <9209232130.AA17014@blarney.MIT.EDU>
To: netusers@MIT.EDU
Cc: net-help@MIT.EDU, network@MIT.EDU
Subject: Building 5 Reconfiguration
The reconfiguration of the building 5 (18.58) network originally set
for Thursday evening at 8:00pm has been moved to Friday morning at
8:00am. As before it is expected to take no more than a half-hour,
and service interruptions should be minimal.
-Chris Murphy