Re: Countdown to release; e-mail check-in

daemon@ATHENA.MIT.EDU (Jonathon Weiss)
Thu Aug 7 18:27:20 2014

From: Jonathon Weiss <jweiss@MIT.EDU>
To: Jonathon Weiss <jweiss@MIT.EDU>
cc: Jonathan D Reed <jdreed@MIT.EDU>,
        "release-team\@mit.edu" <release-team@MIT.EDU>
In-reply-to: Your message of "Wed\, 06 Aug 2014 18\:53\:39 -0400."
             <20140806t185339p2590damsjw@speaker-for-the-dead.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain; charset=utf-8
Date: Thu, 07 Aug 2014 18:27:11 -0400
Message-id: <20140807t182711p13231damsjw@speaker-for-the-dead.mit.edu>
Content-Transfer-Encoding: 8bit


I'm currently looking at Thursday 8/14 at around 1pm for the
athena.dialup.mit.edu upgrade.  This will simply be a DNS change to
point athena.dialup.mit.edu (and ftp.dialup, etc., etc.) at the new
machines.  Existing connections will not be touched at this time.

Do you see any problems with this?  I assume people will be around all
week to deal with any emergencies that crop up after the cluster
upgrades anyway.


	Jonathon



> 
> Yeah, I believe we can commit to before reg day.  I hope to have a specific day picked by the end of the week.
> 
> 	Jonathon
> 
> 
> 
> Jonathan D Reed <jdreed@MIT.EDU> wrote:
> 
> > I don’t need an exact date per se.  Can we commit to “before reg day”?
> > 
> > 
> > On Aug 6, 2014, at 9:08 AM, Jonathon Weiss <jweiss@MIT.EDU> wrote:
> > 
> > > 
> > > I'm afraid I don't have a date for the dialups yet.  I'm hoping for sometime between the 11th and 19th inclusive, but need to check that with both people and other calendars before committing to it.
> > > 
> > > Another issue that was recently brought to my attention is that barnowl in the barnowl locker doesn't work on Trusty.  I forwarded the issue to barnowl-locker last night, but think it's a stupid issue that a recompile is likely to fix.  
> > > 
> > > 
> > > 	Jonathon
> > > 
> > > 
> > > 
> > > 
> > > Jonathan D Reed <jdreed@MIT.EDU> wrote:
> > > 
> > >> As far as I know, we’re on track for Monday Aug 11 for release.  I’m going to flip the “early” bits today, which will mean another 10 machines or so (list sent to acis-team last week) will auto-upgrade over the weekend.  (I will be around and checking on things, but the impact is low.
> > >> 
> > >> Remaining timeline:
> > >> 
> > >> - Today at 5pm: Freeze.  Nothing goes to production, except for bug fixes actively impacting usability, between now and Aug 18.
> > >> - By Tuesday at 10am: Mail to release-announce with final details, and an estimated date for the dialups (jweiss?)
> > >> - Monday, Aug 11: Flip the switch, and let machines upgrade overnight.
> > >> 
> > >> Let’s do e-mail check-in this week, and meet on 8/8 at 2pm (I will send an invite in Exchange).  (2pm works around achernya’s availability; let me know if anyone else has conflicts).  I think in general, going forward, I’d prefer to move our standing meeting time to 2pm.
> > >> 
> > >> Outstanding issues:
> > >> - Force logout/unlock screen is klunky:
> > >> — LightDM may be able to give us a knob to disable switch-user functionality at the display manager level, so that would be a win, but we’d also loose the only hook we have to force-logout a user.
> > >> — An upcoming rewrite of the greeter should also fix some of the UI pains
> > >> 
> > >> Anything else I’m missing?
> > >> 
> > >> -Jon
> > 
> 