> 1. The rough schedule for Sol 2.4 and IRIX 5.3 going through the
> release order steps is:
>
> alpha--Feb/March
> beta --April, May, June
> release-- July/Aug
>
> What about early? or do you mean beta when you say alpha and early
> when you say beta. Historically, beta has ment those I/S people who
> felt daring, and early has meant almost all of I/S and a couple of
> cluster machines.
Alpha and Beta in this schedule have no direct correlation to the
traditional friendly (or beta) and early (or staff) test cycles.
Rather, they are stages in the release cycle which are described by
Mike's documents. The things we think of as friendly and early test
come between the above stages labeled "beta" and "release", or possibly
constitute the actual release part.
More details are available at
http://web.mit.edu/mbarker/www/porting/release.html
dot