[934] in I/T Delivery

home help back first fref pref prev next nref lref last post

Windows 2000 Domains & Servers: October 2002 Delivery Report

daemon@ATHENA.MIT.EDU (Kerem B Limon)
Fri Nov 8 14:38:50 2002

Message-Id: <5.1.1.6.2.20021108143812.05b89080@po11.mit.edu>
Date: Fri, 08 Nov 2002 14:38:43 -0500
To: Delivery Process <delivery@mit.edu>
From: Kerem B Limon <kerem.limon@MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

(correction to URL only)

Project Name: Windows 2000 Domains & Servers Delivery Project
Project Leader: Kerem B. Limon
Report Date: November 8, 2002 (for late September 2002 - October 2002)
Project Web site URL: http://web.mit.edu/windows-delivery/

Accomplishments in October:

- Met several times with project sponsors, stakeholders, supporters to 
chart out project goals and objectives. Began work on the detailed project 
work breakdown structure and phases.

- Sent out several communications out to the community, particularly:

	- Delivery Project Announcement to ITPartners, ITAG, InfoSys, September 
24, 2002
	- Delivery Project Pre-planning Update to Infosys, October 23, 2002
	- Delivery Project On-line Information Update, to ITPartners, WinPartners, 
Infosys, October 28, 2002
	(cf. project Web site)

- (Project Leader) responded personally to various community inquiries 
following announcements.

- Presented a project overview at the ITPartners Fall 2002 Conference, to a 
full crowd (very well received, according to community feedback). (cf. 
project Web site)

- Acquired various Athena mailing lists, AFS groups, an Athena locker and 
Discuss archives, tasked appropriately for tracking internal and external 
communications, project progress, and for providing access to shared 
information.

- Prepared and made live a preliminary iteration of the project Web site, 
as promised, following the ITPartners Conference.

- (Project Leader) met personally with each prospective participant and/or 
parties interested to discuss matches and potential roles on the project 
team. Communicated with their superiors to secure various levels of commitment.

- (Project Leader) met with a Competency Group representative to assist 
with team building efforts, managing team dynamics, resolving HR issues.

- Worked closely with the WinAthena Team to identify overlaps and 
reposition resources appropriately to benefit both efforts.

- (Project Leader & WinAthena liaison) began participating in WinAthena 
Team meetings and WinAthena Container Administrators meetings regularly.

- Worked closely with the parallel Windows efforts, including the following:

	- Met with the Building 37 High Performance Cluster team and with the 
assistance of Training & Publications (TPS), hired and tasked a new 
technical writer dedicated to these two projects. Began discussions to 
identify overlaps and common tasks to help lessen documentation load across 
the two efforts.

	- Met with the Professional Learning Center (PLC) team and charted next 
steps in their WinAthena and separate Windows 2000 Domain pilots.

	- Checked in with the Office of Sponsored Programs  (OSP) and Biology 
WinAthena efforts through WinAthena Container Administrators meetings and 
through project leads in these pilots.

- (Project Leader, one key DLC member, along with WinAthena and DITR 
representatives) attended the Microsoft Exchange Conference 2002 in 
Anaheim, CA. Attended various technical sessions on Windows Domains/Active 
Directory, deployment/migration options and resources, installation 
technologies, maintenance and update mechanisms, security issues and 
resources, Exchange Server developments, and future development 
directions/paths for many Microsoft products. Checked in with Microsoft 
representatives, noted new directions in Microsoft's Windows, Windows 
Server, and Exchange Server strategies, explored vendor offerings.

- Engaged several key project team members in the ongoing Microsoft Premier 
Support Services (PSS) effort.

- Met and communicated with technical and sales representatives to MIT from 
Microsoft and Dell to identify potential resources in further stages of the 
project.

- Acquired a cost center and relevant financial resources related to the 
project budget. Made preliminary allocations for project expenses and 
particularly the technical writer position.

- Finished first draft of the Documentation Map and Training Strategy.

- Completed building the project team, including significant participation 
from key DLC representatives and engaging various key IS colleagues and 
groups across the organization.

- Met with the Network Security Team representatives to secure their 
involvement/oversight in the project.

- Successfully held team kick-off meeting and re-examined the project 
overview, established ground rules, and determined team logistics. 
Scheduled weekly team meetings, commencing next week,  Tuesday, November 
12, 2002.

- Completed Project Leader transition to Delivery Process, with some 
related administrative adjustments ongoing.

Goals for November:

- Finalize first version of the project plan and work breakdown structure.

- Commence community outreach with extensive in-person survey and analysis 
of DLCs' Windows use and relevant needs.

- Redesign and finalize website and project team notebook.

- Finalize Documentation Map and Training Strategy.

- Begin development of Design Assistance & Review Team processes, 
documentation, and supporting resources.

- Begin closer communication with ongoing pilot Windows efforts as well as 
DLCs that have already moved/are interested in/constrained to urgently 
moving to Windows 2000 Domain & Server platforms.

Next Community Milestone:

- Redesigned and finalized website and project team notebook. (ASAP)

- Completed in-person survey of DLCs and analysis of their Windows platform 
use from server and client perspectives, key applications & services, needs 
vs. wants. (December)

- Finalize and announce the initial Design Assistance & Review Team (DART). 
(targeted for mid-January)

Issues:

- No major outstanding issues at this time.

Key Learnings:

- As per the preceding Discovery effort, community interest in and 
following for the project remains very high. The ITPartners presentation 
ran full-house (with overflow even) and there is solid, detailed, specific 
feedback coming from various DLC representatives to this team. Part of that 
feedback regarding the project effort itself is positive.

- The fact that this project is attempting to develop the necessary 
resources, processes, and mechanisms to support Windows 2000 Domains & 
Servers at MIT appears to be seen as a welcome (and overdue) gesture by 
DLCs. The fact remains however that our effectively implying they will need 
to hold off another 6-8 months is a concern we will need to address very 
carefully in the coming months, especially in choosing pilots and test cases.

- We need to move aggressively and quickly on identifying our customer base 
and audience in sufficient, relevant detail, in order to make proper and 
realistic assessments of their needs, wants, and expectations, and 
consequently tailor our offerings accordingly, however reasonably and 
feasibly. Our outreach effort beginning immediately is the first step in that.

- There is a real need to negotiate those customer needs, wants, and 
expectations in the face of available resources from IS. With the 
significantly more complicated and feature-rich nature of the Windows 2000 
technologies, it is crucial for our success to establish a common 
understanding and reasonable expectations and responsibilities across 
service & support providers in IS and their counterparts in DLCs, in both 
directions. This is essential in preventing both sides from over-planning 
and under-committing necessary resources. The Design Assistance & Review 
Team is a key component of this attempt.

- The time is right to involve various peer-to-peer community support 
organizations and user groups, such as ITPartners, WinPartners, 
MacPartners, etc. in a more organized and connected fashion to 'extend' IS' 
support into the DLCs and ultimately their customers. There is significant 
first-hand experience within these communities, and a daily exchange of 
useful information that is neither being effectively captured nor 
extensively publicized when appropriate. As far as this project team is 
concerned, these groups (of which many of the team members, IS or DLC are 
active participants) represent a key link in reaching out to our community. 
The project leader continues to remain in close conversations and planning 
with Support colleagues from SWRT and Support HQ regarding these possibilities.

- This project has great potential for IS to "re-engage" DLCs, particularly 
those who feel disenfranchised or disillusioned by IS' current (and recent 
past) Windows NT 4.0 stance and overall Windows platform support. In the 
same vein, this project represents a significant opportunity to help set 
the tone of Windows support at MIT for the foreseeable future.

Team Dynamics:

- Excellent. Good rapport across various participants and openly expressed 
eagerness to move forward.

Additional Comments:

- None at this time. 


home help back first fref pref prev next nref lref last post